USA: American Electric Power (AEP) has selected Jacobs and WSP USA to support a $37 B transmission investment programme across 11 states, as it prepares for rising electricity demand from data centres and industrial developments.

The programme forms part of AEP’s $100 B capital investment plan for 2027–2031. Transmission spending comprises $17 B for Regional Transmission Organization-driven projects, $11 B for reliability and asset modernisation, and $9 B for customer connections.

Jacobs will lead programme management across AEP’s seven-state eastern territory. Its scope includes engineering design, project controls, environmental compliance, right-of-way acquisition and public outreach, supported by ORC, GFT and RC Commonwealth.

WSP USA will lead delivery across the four-state western territory, covering system planning, environmental permitting, engineering and programme management. Individual contract values were not disclosed.

AEP reported 15 GW of new customer load commitments during the third quarter, bringing projected incremental contracted demand to 84 GW by 2031. According to its investor presentation, 92% relates to data centres and high-density computing facilities, including cryptocurrency operations.

The utility plans to nearly triple the mileage of its 765 kV network. A major project is a $5 B transmission development in southern Ohio, intended to supply SB Energy’s planned 10.4 GW data centre campus in Piketon.

Three 765 kV lines would connect the campus with AEP substations near Cheshire and Hanging Rock. Construction is scheduled to begin in the first quarter of 2027, with targeted in-service dates in late 2028, 2029 and 2030. An initial 800 MW of demand will be served by existing infrastructure.

Source: BIC Magazine