UK: Balfour Beatty has reported a $2.8 B (£2.1 B) power transmission order book, up from $2.1 B (£1.6 B) at the previous year-end. First-half revenue reached $488 M (£366 M).
The company’s work includes overhead lines, cabling and substations, supported by long-term frameworks with National Grid, SSE and ScottishPower. It also sees opportunities in HVDC converter stations, interconnectors and distribution networks.
Balfour Beatty said early procurement is becoming increasingly important as lead times lengthen for conductors and substation components. Longer-term customer agreements are supporting investment in supply chains, training and delivery capacity.
Its steel manufacturing business, Painter Brothers, has doubled output from 5,000 to 10,000 t and is targeting 15,000 t alongside further factory expansion. It produces transmission towers, gantries and substation structures.
The company has recruited more than 1,700 people over three years. Its combined direct and supply-chain workforce could grow from around 3,200 to as many as 6,000, according to its projections.
Projects include Woolavington substation in Somerset, Netherton Hub in northeast Scotland and the Beauly-to-Peterhead overhead line scheme, comprising 620 towers across 187 km.
Source: TradingView