UK: Grid or network readiness is among the three biggest barriers to delivering energy infrastructure for 59 % of UK respondents, according to Jacobs’ Energy Readiness Equation report.

The UK recorded the highest proportion across the five countries surveyed, ahead of the US at 51 % and Germany, Australia and Singapore at 48 % each.

The research also identified obstacles to investment. While 69 % of UK respondents believe sufficient capital is available, 38 % report a shortage of projects ready to attract investment. Policy or regulatory uncertainty was among the three leading barriers to investment readiness for 70 %, while 66 % identified permitting or land constraints.

A Statkraft case study in the report illustrates how more flexible operating arrangements could shorten connection delays. The initial connection timetable for a battery project was reduced from seven years to two after the project team and system operator examined network constraints in greater detail.

The proposed approach included accepting curtailment during constrained periods, allowing an earlier connection rather than waiting for upgrades that would permit unrestricted operation.

Source: Electrical Review