UK, Tilbury: National Grid has completed tunnelling on its Grain to Tilbury project, following the breakthrough of tunnel boring machine Caroline beneath the River Thames.
The 2.2 km high-voltage electricity cable tunnel runs between Tilbury in Essex and Gravesend in Kent and forms part of National Grid’s Great Grid Upgrade programme.
The tunnelling phase was completed 49 days ahead of schedule. More than 10,000 concrete tunnel segments were installed to create nearly 1,700 tunnel lining rings.
At peak performance, the tunnel boring machine advanced 229 m in one week, while its highest daily output reached 41 m.
The reception shaft at Gravesend was intentionally flooded before breakthrough to balance hydrostatic pressure in the surrounding chalk ground and reduce the risk of groundwater entering the shaft.
National Grid said the project will strengthen the electricity network and support growing electricity demand.
Following the breakthrough, work will continue on the remaining tunnel lining. The Gravesend shaft is being dewatered before the tunnel boring machine is lifted and dismantled as the project moves into its next construction phase.
Source: National Grid