Italy, Ragusa: Work on the second Malta–Italy electricity interconnector (IC2) includes connecting a newly installed 220 kV reactor to a hybrid switchgear module at Ragusa Substation in Sicily.

The reactor will be connected using high-voltage cables routed through trenches prepared during an earlier shutdown of the existing interconnector, IC1. Terna Energy Solutions has also continued assembling and installing the new air-insulated switchgear for IC2.

IC1 is scheduled to be shut down for eight days from 27 October while the work is carried out. Local generation will cover Malta’s electricity needs during the interruption.

Following the cable connection, installation, integration and testing will continue at the terminal station. Commissioning is planned for later next year.

The $334 M (€300 M) IC2 project includes a 225 MW, approximately 122 km submarine cable between Magħtab in Malta and Ragusa. The 245 kV link is designed to double Malta’s electricity interconnection capacity and is co-financed by the European Union through the European Regional Development Fund.

Source: Malta Today