UK, Scotland: SP Energy Networks has published revised proposals for major upgrades to the electricity transmission network in Fife.

The plans form part of a long-term investment programme to support regional economic growth, increase network capacity and maintain a secure and reliable electricity supply for future generations.

As electricity demand across Scotland is expected to double by 2050, SP Energy Networks is proposing to extend Mossmorran substation near Cowdenbeath and increase the voltage of existing overhead transmission lines in Fife.

The upgrades are intended to create additional capacity on the network, allowing more renewable energy to be transported efficiently from where it is generated to homes and businesses across the country.

The company is seeking feedback from local communities on the updated plans. Comments received during the consultation will help shape the final design, including the substation layout, access, drainage and landscaping.

SP Energy Networks said much of Scotland’s transmission network was built between 50 and 100 years ago. While the system has developed over time, parts of the network are now approaching operational limits as more wind, solar and battery storage projects seek to connect.

To support this growth, overhead lines between Tealing and Kincardine will be upgraded from 275 kV to 400 kV. The work also requires upgrades at Mossmorran and Westfield substations and a new substation at Conland, north of Leslie.