USA, North Carolina: WhiteFiber has reported switchgear-related commissioning issues at its NC-1 data centre campus in Madison, interrupting service and billing for its first 20 MW IT data hall.

The issues delayed full contracted run-rate billing beyond August, when the company had expected to reach that milestone. The disclosure did not identify the switchgear manufacturer or specify the technical cause.

Approximately 35 MW of the 40 MW critical IT deployment contracted to Nscale is operational, with work continuing on the remaining 5 MW. The ten-year agreement represents approximately $865 M in contracted revenue.

WhiteFiber said most capital investment for NC-1’s initial deployment has been completed and total development costs are expected to remain within budget.

Separately, subsidiary Enovum Data Centers completed a $60 M cash acquisition of two industrial properties in Yadkin County, designated NC-2 and NC-3.

The properties cover approximately 120 acres and contain 500,000 square feet of warehouse space. WhiteFiber plans to convert them into data centre campuses, with at least 60 MW of initial gross utility capacity expected and initial ready-for-service capacity targeted for late 2027.

The company estimates potential capacity of approximately 200 MW within seven years of closing, subject to confirmation and power availability. No tenants have signed definitive agreements for the new sites. Development spending will depend on customer contracts and financing.