USA, Encinal: A $22 B power project is planned in La Salle County, Texas, combining a 6.47 GW combined-cycle gas power plant with a neighbouring 5 GW data centre.
According to the US Department of Commerce, the project is being developed with support from the United States and South Korean governments. The power plant will be operated by Related Companies and NextEra Energy Resources.
The first phase is expected to enter operation in 2029, with the facility reaching full capacity in 2032.
Most of the electricity generated will directly supply the adjacent data centre, while remaining capacity will be delivered to the Texas power grid.
The data centre is planned with a closed-loop water cooling system. The project is also examining the potential use of produced water, a by-product of oil and natural gas extraction, for cooling.
Construction is expected to create around 8,400 jobs, while the completed power campus and data centre are expected to support hundreds of permanent positions.
Source: Fox 7 Austin