Moldova: VIM Energy Systems AB, a subsidiary of Vimab Group, has secured a contract worth approximately $20 M (SEK 190 M) to deliver a new battery energy storage facility in Moldova.
The order was placed by Esco-Voltaj SRL for delivery to state-owned energy company CET-Nord. VIM Energy’s scope includes the design, supply, installation and commissioning of the complete energy storage system.
The project is expected to be completed in the first quarter of 2027, with payments linked to project milestones. The first payment will be made following contract signing and placement of the order.
The award is VIM Energy’s second order in Eastern Europe in a short period. The company has also signed a $2.3 M (SEK 22 M) agreement to supply battery systems for a pilot project in Albania.
VIM Energy said it now has projects representing 160 MWh of battery storage capacity outside Sweden. During the summer, the company also completed a 50 MWh battery park in Sweden that had been announced in 2025.
Together, the Moldova and Albania contracts bring the value of VIM Energy’s battery-storage orders secured so far in the third quarter of 2026 to approximately $22 M (SEK 210 M).
Peter Fredell, CEO of Vimab Group, said the Moldova project strengthens the company’s position in the Eastern European market following several years of activity in the region.