HSM secures EA2 substation deal

ScottishPower Renewables has awarded HSM Offshore Energy an EPCIC contract for the 960 MW East Anglia 2 offshore substation and jacket foundation.

 


offshore wind turbines_shutterstock_2465469885

Image for illustration purposes

UK: HSM will supply a 5,100 mt high-voltage offshore substation and a 3,700 mt jacket foundation for the project off the Suffolk coast. Initial engineering work began in summer 2024 under an early agreement, with construction set to begin in Q4 2025. The jacket installation is scheduled for Q3 2027, followed by the topside installation in late 2027.

Hans Leerdam, CCO at HSM Offshore Energy, commented, “This contract is a key milestone for HSM Offshore Energy, reinforcing our role as a trusted partner in offshore wind. ScottishPower Renewables’ proactive approach in securing yard capacity early highlights the importance of collaboration in driving the energy transition.”

Ross Ovens, MD for offshore at ScottishPower Renewables, added, “We’re excited to work with HSM Offshore Energy to bring the $5 B (£4 B) East Anglia TWO wind farm to life, supporting the UK’s green energy goals. This contract exemplifies our forward-thinking strategy in securing top-tier supply chain partners early.”

Located 33 km from Southwold and 37 km from Lowestoft in the southern North Sea, the East Anglia 2 offshore wind farm will provide power to nearly one million homes once operational.